Bathrooms by DRC This is in the Northwood area.
9 6
18 days ago
If your free or in the area with the family. I'll be on a badge making stall. Enjoy the weekend all
3 0
10 months ago
All you have to do is Zoom in on The bubble on the both levels. These steel beams are only bearing on 4 stacks of blocks .... At the time we are only hust painting with a galafoid paint. Nice! Pic 📸.... Testiment to the level concrete RC piled slab. #bonified
7 0
1 year ago
Another completed bathroom for 2025. Let us fresh up your bathing experience. All you need to do is call.
9 0
1 year ago
Friday! Update for DRC. Something to look at while you getting ready to hit the town, or on the couch.enjoy.
17 0
1 year ago
I was meant to update Friday just passed. But I thought it was a nicer surprise for the clients to see the brickwork at our meeting today. Now that it has been cleaned and sealed etc. Many hours of work there! The brickwork on the ground floor is now covered do that any render work on the first floor does stain the hard work below. Ply walls are formed and soon ready for first fix electrics. best Dan.
10 1
1 year ago
Last week's work and update. This week UKPN and Affinity Water connections and the insulation is to arrive
10 0
1 year ago
Update on our new Infill house build. Dates are set now for the UKPN & affinity water to make their connections. First floor timber construction is complete and the drainage continued to the first floor. Walls for the first floor will certainly be completed by next week. This would then be ready for roof construction once the brickwork has been completed to the first floor. The scaffolding can then be erected for the process. Hope your enjoying the summer holidays and if your plans to improve your home in some way are on your mind.... We're on the end of your first phone call to discuss. :) Best Dan.
10 0
1 year ago
The Bushey project had been signed off by building control last week. We are delighted with the outcome. Further decorating and furnishing will be ongoing I'm sure. But it looks fantastic 😍
6 0
1 year ago
Alot of steel fabric has been completed. Probably 40% over engineered for a timber structure. A few checks then ready for the concrete pour.
4 0
1 year ago
Our Bushey project, and the snagging list created by the local building control has been completed today. More satisfied customers #DRC Project completed. Final completed pictures to follow once decorated and furnished